The concrete boot for the Little Pine Island Bridge is now planned for Friday, March 28th, at 2 a.m.
When the work is resumed, the crews pour more than 300 meters of concrete for the cover plate that take about five hours.
Expect an increased noise, additional lighting and potential traffic jams during operation.
Uncertainty is always a factor in assessing the effects of the construction on the flow of traffic. In order to stay up to date, drivers are asked to check the FDOT traffic app at www.fl511.com for real-time updates.
At https://www.leegov.com/dot/traffic can be accessed on live bridges -Feeds.
Phase 1 update
We want to complete phase 1 by spring 2025 and make considerable progress on both the east and on the west side of the bridge.
The tree manners ended the formation and binding of the steel deck.
The tree nests have successfully cast with the Eastern approach, whereby the concrete deck and the western approach should follow.
The upcoming activities include plasters and use.